Expired
Milestone
expired on Jun 27, 2016
Milestone-3
Main goals:
- Production readiness of Ceph
Staging environment- Multiple mountpoints delivered
Agreement on monitoring- https://gitlab.com/gitlab-com/operations/issues/42 should load in ~6 seconds by the end of this milestone
Finish runbooks
All issues for this milestone are closed. You may close this milestone now.
Unstarted Issues (open and unassigned)
0
Ongoing Issues (open and assigned)
0
Completed Issues (closed)
11
18
- Monitor Sidekiq queues and restarts
- Provide multiple git mount points
- Build a staging environment for developers only
- Improve monitoring
- Improve infrastructure documentation
- GitLab on CephFS
- Make GitLab.com fast again
- Logs from shared-runners-manager-1 are not reaching ELK
- Redis Server Performance Improvement
- Docker registry logs (?) showing up as wrong program name
- Add runbooks for oncall common situations